90 x 90 mm Aluminium Profile Supply: Stock Planning and Lead Time

OEM / ODM Available Free Sample Available Mill certificate per heat, coating thickness and seal report per anodising lot, one set for the whole quantity

90 x 90 mm eight-slot aluminium extrusion in 6063-T5 for multi-site supply across Maharashtra. 7.60 kg/m, shipped as one lot with labelled bundles and a single anodising rack load per colour.

Wholesale Price Quoted per metre against the split, cut list and finish per metre
Material Aluminium
Alloy Grade 6063-T5
Temper T5
Section Size 90 x 90 mm, eight slots
Slot 8 x 10.2 mm groove, 10 mm mouth, 45 mm pitch, outer pair 45 mm apart
Length 6 m stock; cut to list to +/-0.5 mm
Tolerance EN 755-9, wall +/-0.15 mm; straightness 1.5 mm per metre; twist 2 degrees
Surface Mill finish, or anodised AA15 / AA20 to EN ISO 7599; clear or black; single rack load
MOQ 150 m, or 500 m for a mixed load to two or more sites
Lead Time 25 to 35 days after deposit, plus 16 to 24 days ocean and 1 to 6 days inland depending on the city
Loading Port Shanghai / Ningbo
Supply Ability 600 t per month extrusion with in-house anodising
Payment Terms T/T 30% deposit + 70% before shipment | L/C at sight
Trade Terms FOB | CIF | DAP
Certifications Mill certificate per heat, coating thickness and seal report per anodising lot, one set for the whole quantity
Request a Quote Reply within 24 hours
90 x 90 mm eight slot aluminium profiles stored in a covered warehouse with moisture protection before distribution across Maharashtra
Anodised stock sitting through a monsoon in an open shed is a corrosion question before it is a space question. Film thickness does not stop pitting when water sits in a slot for three months.

01Where should the stock actually sit?

One place, in almost every case. The instinct is to hold a little stock at each site so that nobody waits, and the arithmetic usually says the opposite: three small stocks carry more total capital than one larger one, because each has to cover its own variability, and none of them can help the others.

The exception is when the sites are far enough apart that a transfer costs more than the extra stock. Pune to Nagpur is about 700 km, which is a day and a half by road and a real cost per tonne. Beyond roughly 500 km, a second stocking point starts to make sense for fast-moving sections, and for a slow-moving section like 90 x 90 it usually still does not.

02How much safety stock does the distance actually require?

The standard model is safety stock equals Z times the standard deviation of demand times the square root of the lead time, with demand and lead time in the same unit. The square root is the part people skip, and it is the part that makes distance less frightening than it feels.

A worked example. Suppose the demand for this section is 120 m a day with a standard deviation of 40 m, and the replenishment lead time is 12 days for a domestic transfer. At a 95 percent service level, Z is 1.65. Safety stock is 1.65 times 40 times the square root of 12, which is about 228 m. If the lead time doubles to 48 days for an import, safety stock becomes 1.65 times 40 times the square root of 48, about 456 m. Doubling the lead time increases the buffer by a factor of two, not four.

Lead timeSquare rootSafety stock at Z 1.65, sigma 40Comment
6 days2.45162 mDomestic transfer, close sites
12 days3.46228 mDomestic transfer, Pune to Nagpur
24 days4.90323 mImport plus inland
48 days6.93457 mImport plus a slow sailing

The model is only as good as the standard deviation, and most buyers do not have one. If you have three months of issue data, you can calculate it. If you do not, start with a buffer equal to two weeks of average demand and adjust after a quarter, rather than trying to derive a number you cannot support.

03What does the lead time map look like?

Four destinations matter for most Maharashtra buyers, and the difference between them is inland transit rather than ocean. The ocean leg is common to all of them.

DestinationOcean legInland from portTotal to site
Mumbai and Navi Mumbai16 to 22 days to Nhava ShevaSame day to 1 day17 to 23 days
Pune16 to 22 days to Nhava Sheva2 to 3 days18 to 25 days
Nashik16 to 22 days to Nhava Sheva2 to 4 days18 to 26 days
Nagpur16 to 24 days to Nhava Sheva or Mundra4 to 6 days20 to 30 days
Aurangabad16 to 22 days to Nhava Sheva3 to 5 days19 to 27 days

Add the production lead time to these figures, not to the sailing alone. For a 90 x 90 with an existing die and mill finish, production is 12 to 20 days, so a Nagpur delivery is realistically 32 to 50 days from order. That number, not the sailing, is what the safety stock has to cover.

04What does a monsoon do to stored anodised stock?

It pits it, in the slots, where water sits. An anodic film is corrosion resistant because it is a barrier, and a barrier works while it is intact and while the environment is not permanently wet. Water standing in an open slot for weeks is the one condition the film handles worst, and the pits that form are inside the slot where nobody sees them until assembly.

The practical controls are cheap: store under cover, store at an angle so water runs off rather than sitting, keep the bundles off a damp floor on timber, and do not remove the interleaving until the material is issued. For long storage, a strippable tape on the open slots costs very little.

Monsoon storage checklist

  • Covered shed, not open yard, from June to September.
  • Bundles on timber bearers, not directly on a concrete floor that draws damp.
  • Stored at a slight angle along the length, so water cannot pool in a slot.
  • Interleaving left in place until issue, not stripped on receipt.
  • FIFO discipline, because the bundle that sits for a year is the one that pits.

05How do you keep one batch traceable across three cities?

By treating the batch as a unit and splitting it deliberately, rather than by ordering three times and hoping. The mechanism is simple: one extrusion lot, one anodising rack load, one heat number, split into bundles that are labelled with the same reference before they leave.

The failure mode is subtle. Two anodising lots of the same section look identical in isolation and different side by side, because film thickness varies with position on the rack and a thicker film reads darker. If the two lots go to two cities, nobody notices until a project spans both sites.

One lot, split by bundle

  • Single heat number and single anodising rack load
  • Colour is consistent across all sites
  • One set of certificates covers the whole delivery
  • Requires ordering the total quantity at once

Three separate orders

  • Three heat numbers and three rack loads
  • Colour difference is likely and hard to attribute
  • Three sets of certificates to reconcile
  • Lower commitment per order, higher total risk

The cost of the single lot is that the total quantity has to be committed at once, which is working capital. The cost of three lots is a colour mismatch across sites, which is usually more expensive and much harder to fix after the frames are built.

06What five numbers should be on the enquiry?

A multi-site enquiry needs the split and the schedule, not just the total.

Total quantity and split
metres per site, because the bundle allocation follows the split
Delivery dates per site
staggered deliveries change the production planning
Finish and colour
one rack load per colour, stated so the lots are not split
Length and cut
6 m stock or cut to list, per site
Storage at destination
covered or open, because it changes the packing advice
Section
90 x 90 mm eight slot at 7.60 kg/m, or the heavy wall at 9.00 kg/m

Send the split by city and the delivery dates

  1. 90 x 90 mm, 6063-T5, eight 10.2 mm slots, 7.60 kg/m
  2. 900 m total, split 400 Pune, 300 Nashik, 200 Nagpur
  3. AA15 anodised clear, one rack load for the whole quantity
  4. Bundles labelled by destination before dispatch
  5. Covered storage confirmed at each site

Ask for the whole quantity in one anodising rack load even when it ships to three cities. It is the only way the colour stays consistent, and splitting the anodising is how multi-site projects end up with two shades.

Related sections and categories

The 90 x 90 is listed under 45 Series Aluminium Profiles, with the heavy wall version at 9.00 kg/m. For lighter frame work the 45 x 90 mm six slot section at 4.10 kg/m halves the freight per metre.

Should I hold stock at each site or centrally?

Centrally, in almost every case. Three small stocks carry more total capital than one larger one, because each has to cover its own demand variability and none can help the others. A second stocking point starts to make sense beyond roughly 500 km, and only for sections used weekly rather than quarterly.

How do I calculate the safety stock for a long lead time?

Safety stock equals Z times the standard deviation of demand times the square root of the lead time. At a 95 percent service level Z is 1.65. With a daily standard deviation of 40 m and a 48 day lead time, the buffer is about 457 m. The square root is the important part: doubling the lead time doubles the buffer rather than quadrupling it.

Does anodised stock corrode in a monsoon?

It pits, particularly inside open slots where water sits for weeks. The film is a barrier and it handles that environment poorly when it is permanently wet. Store under cover, on timber bearers, at a slight angle so water runs off, and leave the interleaving in place until issue.

How do I keep colour consistent across three cities?

One extrusion lot and one anodising rack load for the whole quantity, split into labelled bundles before dispatch. Film thickness varies with position on the rack and a thicker film reads darker, so two rack loads of the same section can look different side by side while each looks fine alone.

What is the realistic lead time to Nagpur?

About 32 to 50 days from order, made up of 12 to 20 days production, 16 to 24 days ocean to Nhava Sheva or Mundra, and 4 to 6 days inland. Quoting the sailing alone understates it by roughly three weeks, which is the gap that safety stock has to cover.

Send the split by city and the delivery dates

Tell us how the metres divide across sites, when each one needs material, and whether storage is covered. We will come back with a bundle plan, one rack load per colour, and certificates issued once for the lot.

Request a quotation