90 x 90 mm eight-slot aluminium extrusion in 6063-T5 for multi-site supply across Maharashtra. 7.60 kg/m, shipped as one lot with labelled bundles and a single anodising rack load per colour.
| Material | Aluminium |
|---|---|
| Alloy Grade | 6063-T5 |
| Temper | T5 |
| Section Size | 90 x 90 mm, eight slots |
| Slot | 8 x 10.2 mm groove, 10 mm mouth, 45 mm pitch, outer pair 45 mm apart |
| Length | 6 m stock; cut to list to +/-0.5 mm |
| Tolerance | EN 755-9, wall +/-0.15 mm; straightness 1.5 mm per metre; twist 2 degrees |
| Surface | Mill finish, or anodised AA15 / AA20 to EN ISO 7599; clear or black; single rack load |
| MOQ | 150 m, or 500 m for a mixed load to two or more sites |
| Lead Time | 25 to 35 days after deposit, plus 16 to 24 days ocean and 1 to 6 days inland depending on the city |
| Loading Port | Shanghai / Ningbo |
| Supply Ability | 600 t per month extrusion with in-house anodising |
| Payment Terms | T/T 30% deposit + 70% before shipment | L/C at sight |
| Trade Terms | FOB | CIF | DAP |
| Certifications | Mill certificate per heat, coating thickness and seal report per anodising lot, one set for the whole quantity |

One place, in almost every case. The instinct is to hold a little stock at each site so that nobody waits, and the arithmetic usually says the opposite: three small stocks carry more total capital than one larger one, because each has to cover its own variability, and none of them can help the others.
The exception is when the sites are far enough apart that a transfer costs more than the extra stock. Pune to Nagpur is about 700 km, which is a day and a half by road and a real cost per tonne. Beyond roughly 500 km, a second stocking point starts to make sense for fast-moving sections, and for a slow-moving section like 90 x 90 it usually still does not.
The standard model is safety stock equals Z times the standard deviation of demand times the square root of the lead time, with demand and lead time in the same unit. The square root is the part people skip, and it is the part that makes distance less frightening than it feels.
A worked example. Suppose the demand for this section is 120 m a day with a standard deviation of 40 m, and the replenishment lead time is 12 days for a domestic transfer. At a 95 percent service level, Z is 1.65. Safety stock is 1.65 times 40 times the square root of 12, which is about 228 m. If the lead time doubles to 48 days for an import, safety stock becomes 1.65 times 40 times the square root of 48, about 456 m. Doubling the lead time increases the buffer by a factor of two, not four.
| Lead time | Square root | Safety stock at Z 1.65, sigma 40 | Comment |
|---|---|---|---|
| 6 days | 2.45 | 162 m | Domestic transfer, close sites |
| 12 days | 3.46 | 228 m | Domestic transfer, Pune to Nagpur |
| 24 days | 4.90 | 323 m | Import plus inland |
| 48 days | 6.93 | 457 m | Import plus a slow sailing |
The model is only as good as the standard deviation, and most buyers do not have one. If you have three months of issue data, you can calculate it. If you do not, start with a buffer equal to two weeks of average demand and adjust after a quarter, rather than trying to derive a number you cannot support.
Four destinations matter for most Maharashtra buyers, and the difference between them is inland transit rather than ocean. The ocean leg is common to all of them.
| Destination | Ocean leg | Inland from port | Total to site |
|---|---|---|---|
| Mumbai and Navi Mumbai | 16 to 22 days to Nhava Sheva | Same day to 1 day | 17 to 23 days |
| Pune | 16 to 22 days to Nhava Sheva | 2 to 3 days | 18 to 25 days |
| Nashik | 16 to 22 days to Nhava Sheva | 2 to 4 days | 18 to 26 days |
| Nagpur | 16 to 24 days to Nhava Sheva or Mundra | 4 to 6 days | 20 to 30 days |
| Aurangabad | 16 to 22 days to Nhava Sheva | 3 to 5 days | 19 to 27 days |
Add the production lead time to these figures, not to the sailing alone. For a 90 x 90 with an existing die and mill finish, production is 12 to 20 days, so a Nagpur delivery is realistically 32 to 50 days from order. That number, not the sailing, is what the safety stock has to cover.
It pits it, in the slots, where water sits. An anodic film is corrosion resistant because it is a barrier, and a barrier works while it is intact and while the environment is not permanently wet. Water standing in an open slot for weeks is the one condition the film handles worst, and the pits that form are inside the slot where nobody sees them until assembly.
The practical controls are cheap: store under cover, store at an angle so water runs off rather than sitting, keep the bundles off a damp floor on timber, and do not remove the interleaving until the material is issued. For long storage, a strippable tape on the open slots costs very little.
By treating the batch as a unit and splitting it deliberately, rather than by ordering three times and hoping. The mechanism is simple: one extrusion lot, one anodising rack load, one heat number, split into bundles that are labelled with the same reference before they leave.
The failure mode is subtle. Two anodising lots of the same section look identical in isolation and different side by side, because film thickness varies with position on the rack and a thicker film reads darker. If the two lots go to two cities, nobody notices until a project spans both sites.
The cost of the single lot is that the total quantity has to be committed at once, which is working capital. The cost of three lots is a colour mismatch across sites, which is usually more expensive and much harder to fix after the frames are built.
A multi-site enquiry needs the split and the schedule, not just the total.
Ask for the whole quantity in one anodising rack load even when it ships to three cities. It is the only way the colour stays consistent, and splitting the anodising is how multi-site projects end up with two shades.
The 90 x 90 is listed under 45 Series Aluminium Profiles, with the heavy wall version at 9.00 kg/m. For lighter frame work the 45 x 90 mm six slot section at 4.10 kg/m halves the freight per metre.
Centrally, in almost every case. Three small stocks carry more total capital than one larger one, because each has to cover its own demand variability and none can help the others. A second stocking point starts to make sense beyond roughly 500 km, and only for sections used weekly rather than quarterly.
Safety stock equals Z times the standard deviation of demand times the square root of the lead time. At a 95 percent service level Z is 1.65. With a daily standard deviation of 40 m and a 48 day lead time, the buffer is about 457 m. The square root is the important part: doubling the lead time doubles the buffer rather than quadrupling it.
It pits, particularly inside open slots where water sits for weeks. The film is a barrier and it handles that environment poorly when it is permanently wet. Store under cover, on timber bearers, at a slight angle so water runs off, and leave the interleaving in place until issue.
One extrusion lot and one anodising rack load for the whole quantity, split into labelled bundles before dispatch. Film thickness varies with position on the rack and a thicker film reads darker, so two rack loads of the same section can look different side by side while each looks fine alone.
About 32 to 50 days from order, made up of 12 to 20 days production, 16 to 24 days ocean to Nhava Sheva or Mundra, and 4 to 6 days inland. Quoting the sailing alone understates it by roughly three weeks, which is the gap that safety stock has to cover.
Tell us how the metres divide across sites, when each one needs material, and whether storage is covered. We will come back with a bundle plan, one rack load per colour, and certificates issued once for the lot.
Request a quotation