Logistics · die status, finish, sea transit

Aluminium Extrusion Lead Time

Door-to-door for a China T-slot order is typically 30-40 days (30–40) with a new die and anodising, or 12–20 days on an existing die in mill finish, plus about 18 days at sea from Shanghai or Ningbo. The calendar is production stages first, ocean second.

New die + anodising
30–40 days production
Existing die, mill
12–20 days production
Sea freight
+18 days typical
Read
10 minutes
Large aluminium extrusion press in a bright factory with stacked profiles nearby

Short answer

Lead time splits into five stages: quotation and PO lock, die making when the tool is new (7–12 days), extrusion on the press, anodising or other finish, then packing and sailing. The bottleneck on a first order is almost always the die; on a repeat anodised order it is often the colour-batch slot; on mill-finish repeats it is press queue. Capacity context is about 600 t per month of extrusion with in-house anodising. Packing is an ISPM 15 timber cradle with IPPC mark, or a plywood case for cut lengths under 3 m. Add ~18 days sea after the goods leave Shanghai or Ningbo unless you air-freight samples.

Steel extrusion die suspended by hoist near an aluminium extrusion press platen
Existing dies queue faster; new tooling adds design, die making and first-article time before production metres start.

How fast can you ship 100 m of 2020 for an urgent project

Urgent 100 m of 2020 off an existing die in mill finish can leave in about 12–16 days; the same metres with silver anodising usually need 18–25 days; a new die pushes the first bar into the 30–40 day band before sea.

Quantity inside a few tonnes does not change the die clock. 100 m, 500 m, 1 tonne (~2 000 m of 2020 at 0.50 kg/m) and 2 tonnes share the same tooling path; what changes is press hours and whether the lot fills an anodising rack efficiently. For a true rush, mill finish on an existing die is the lever that removes both tooling and bath time. Air freight after production is for samples and short bars, not for a full tonne of 6 m stock. Confirm the die number on the RFQ so the planner does not book a new-tool slot by mistake.

How long does it take to get a quotation

A complete RFQ — section or DXF, alloy, finish, length, quantity, Incoterm and port — returns a quotation in one to two working days.

Missing die status or finish is what stretches quotes into a week, because the planner cannot choose between the 12–20 day and 30–40 day calendars. Metal is indexed to the billet band on the quote date; validity is typically 14 days. Parallel questions on how die cost amortises per meter and minimum order with a new die should sit on the same enquiry so price and calendar are issued together.

How long does a custom profile take from drawing to sample

From approved drawing to first sample bar is typically 7–12 days for die making plus a short press and finish trial — about two to three weeks before you hold metal, then production follows the new-die calendar.

The drawing must freeze wall, slot and CCD before steel is cut; late tweaks reset the die clock. Sample length is usually a few metres for fit and anodising colour check. Tooling title is covered under who owns the die; the same page decides whether a later supplier can reuse the tool. Die making is the bottleneck on this path — not the press itself.

What is the fastest delivery for to (by size)

Fastest production delivery to a named overseas port is existing-die mill finish in 12–20 days plus ~18 days sea; anodised existing-die work lands closer to 18–28 days production plus sea; new-die anodised work sits at 30–40 days plus sea.

The table collapses destination asks (US, Germany, and others) onto one production grid: ocean is the same ~18-day adder on common lanes once the container sails from Shanghai or Ningbo. Section changes packing density and 40HQ fill, not the die clock.

SectionStock lengthsPackingQty per 40HQLead time
100×1006.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
160×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
20×206.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
30×306.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
40×406.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
40×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
45×456.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
45×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~2,800 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
50×506.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
80×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m12–20 d mill / 18–28 d anodised existing die; +18 d sea
90×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m12–20 d mill / 18–28 d anodised existing die; +18 d sea

What is the sample lead time for (by size)

Sample lead time is 5–10 days cut from existing-die stock when metal is on the rack, or 14–25 days when a short press and anodising trial are required; new-die samples follow the 7–12 day tooling gate first.

Samples under 3 m ship in plywood cases; longer bars use the same ISPM 15 cradle logic as production. Air freight after the sample is ready typically adds three to seven days door-to-door depending on the airport pair.

SectionStock lengthsPackingQty per 40HQLead time
100×1006.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
160×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
20×206.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
30×306.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
40×406.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
40×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
45×456.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
45×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~2,800 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
50×506.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
80×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea
90×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m5–10 d from rack; 14–25 d short press + anodise; +air or +18 d sea

Do you keep in stock for immediate dispatch (by size)

Common 20×20, 30×30, 40×40 and 45×45 silver-anodised bars are held as rotating stock for short dispatch; heavy 80×80, 90×90, 100×100 and 160×80 are usually press-to-order.

“Immediate” here means pick, pack and document within a few days when the SKU is on the rack — not same-day container sailing. Stock depths move with season; always confirm metres available before promising a customer’s install date. Non-stock sections fall back to the existing-die or new-die calendars above.

SectionStock lengthsPackingQty per 40HQLead time
100×1006.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 mPress-to-order; use existing-die calendar
160×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 mPress-to-order; use existing-die calendar
20×206.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 mRotating stock; pick/pack in 2–5 days when on rack
30×306.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 mRotating stock; pick/pack in 2–5 days when on rack
40×406.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 mRotating stock; pick/pack in 2–5 days when on rack
40×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 mRotating stock; pick/pack in 2–5 days when on rack
45×456.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 mRotating stock; pick/pack in 2–5 days when on rack
45×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~2,800 mPress-to-order; use existing-die calendar
50×506.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 mRotating stock; pick/pack in 2–5 days when on rack
80×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 mPress-to-order; use existing-die calendar
90×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 mPress-to-order; use existing-die calendar

What is the lead time for on an existing die (by size)

On an existing die, expect 12–20 days for mill finish and about 18–28 days when silver anodising is included, before the ~18-day sea adder.

Section mass changes press hours slightly but does not reopen tooling. Black anodising or a special RAL powder coat can add a bath or cure queue beyond the silver band. The five-stage split for planning is: (1) PO and deposit 1–2 days, (2) die skip = 0 days, (3) extrusion 5–10 days, (4) anodising 5–10 days or 0 if mill, (5) pack and load 2–3 days, then sea.

SectionStock lengthsPackingQty per 40HQLead time
100×1006.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m12–20 d mill; 18–28 d silver anodised; +18 d sea
160×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,200 m12–20 d mill; 18–28 d silver anodised; +18 d sea
20×206.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m12–20 d mill; 18–28 d silver anodised; +18 d sea
30×306.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~14,000 m12–20 d mill; 18–28 d silver anodised; +18 d sea
40×406.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m12–20 d mill; 18–28 d silver anodised; +18 d sea
40×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m12–20 d mill; 18–28 d silver anodised; +18 d sea
45×456.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~7,000 m12–20 d mill; 18–28 d silver anodised; +18 d sea
45×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~2,800 m12–20 d mill; 18–28 d silver anodised; +18 d sea
50×506.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~4,500 m12–20 d mill; 18–28 d silver anodised; +18 d sea
80×806.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m12–20 d mill; 18–28 d silver anodised; +18 d sea
90×906.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark~1,800 m12–20 d mill; 18–28 d silver anodised; +18 d sea

What is the lead time for repeat orders of (by variant)

Repeat orders on a proven die and finish compress toward the bottom of the existing-die band; quantity changes press hours and freight mode more than the start date.

Die making does not recur, which is why die making adds 7–12 days only on the first tool path. Large repeats that fill a 40HQ often clear documents faster because packing is a single FCL pattern.

SectionStock lengthsPackingQty per 40HQLead time
Repeat 100 m6.02 m stock bars (5.8 / 6.0 m on request)Plywood case if cut <3 m; else ISPM 15 cradleLCL / share container12–18 d mill; 18–25 d anodised; +18 d sea
Repeat 500 m6.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC markLCL or part 40HQ12–18 d mill; 18–25 d anodised; +18 d sea
Repeat 1 tonne6.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC markPart / full 40HQ by section14–20 d mill; 18–28 d anodised; +18 d sea
Repeat 2 tonnes6.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC markOften FCL14–20 d mill; 18–28 d anodised; +18 d sea
Repeat 5 tonnes6.02 m stock bars (5.8 / 6.0 m on request)ISPM 15 timber cradle, IPPC mark1×40HQ class16–22 d incl. schedule buffer; +18 d sea
Call-off contractAgreed lengthsISPM 15 timber cradle, IPPC markPer releaseHeld press/anodise slots; confirm each release week

RFQ checklist — lead time

  • Die status — existing die number or new tool.
  • Finish — mill, silver, black, or powder coat.
  • Quantity and lengths — metres or tonnes; stock or cut list.
  • Incoterm and port — FOB Shanghai / Ningbo, CIF, DAP or DDP.
  • Need-by date — install or kit date at destination, not only FOB week.

Ask whether the quote calendar already includes the ~18-day sea adder. Factory weeks and door-to-door weeks are different numbers.

Four ways a lead-time promise breaks

Assuming stock on a heavy section80×80 and above are usually press-to-order. Confirm rack metres before you promise a customer.
Forgetting the die gateNew tools add 7–12 days before any bar exists. Existing-die calendars do not apply.
Omitting anodisingMill finish and silver anodising are different weeks. Colour batches queue behind the press.
Counting only productionDoor-to-door needs +18 days sea on common lanes unless you air samples.

Related on this site

Terms used in this article

Existing die
A tool already cut for the section; production skips the 7–12 day die gate.
New die
First tool for a section; bottleneck stage before the press.
Mill finish
As-extruded surface with no anodising; shortest finishing path.
ISPM 15 cradle
Heat-treated timber packing with IPPC mark for export.
40HQ
40-foot high-cube container; fill limited by weight or volume of 6 m bars.

Questions buyers ask

Can you ship to a named port?

Yes. Production ships FOB Shanghai or Ningbo; CIF, DAP and DDP are available to named ports and places. Sea transit is typically about 18 days on common Asia–US and Asia–Europe lanes, added after the production calendar below.

Who handles customs clearance?

Under FOB and CIF the buyer or their broker clears at destination. Under DAP the seller delivers ready for unloading and the buyer clears. Under DDP the seller arranges clearance and duty. State the Incoterm on the PO so the document set matches.

What if the shipment is delayed?

We flag press or anodising slips as soon as the schedule moves, with a revised ship week. Ocean delay after departure is on the carrier schedule; CIF insurance covers defined marine risks. Critical projects should leave buffer beyond the 18-day sea adder.

Do you consolidate small orders?

Yes when several line items share a sailing and Incoterm. Consolidation reduces LCL cost but may wait for the next shared cut-off. Urgent single lines can ship alone as LCL or air for samples.

Also searched as: aluminium extrusion lead time new die, how fast ship 2020 aluminium profile, T-slot production time China, anodising lead time extrusion, existing die delivery aluminium, sample lead time aluminium profile, repeat order aluminium extrusion lead time.

Send die status, finish and need-by date

Tell us existing vs new die, mill vs anodised, metres and the destination port. We return a production week plus the ~18-day sea adder so you can plan door-to-door.

Request a lead-time sheet